Q#1 Numerical Ability GATE EE 2010 MCQ +2 marks -0.66 marks

5 skilled workers can build a wall in 20 days; 8 semi-skilled workers can build a wall in 25 days; 10 unskilled workers can build a wall in 30 days. If a team has 2 skilled, 6 semi-skilled and 5 unskilled workers. How long will it take to build the wall?

20 days

18 days

16 days

15 days

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 259 0 0
Signals and Systems 164 0 0
Control Systems 201 0 0
Analog Electronics 180 0 0
Digital Electronics 148 0 0
Electrical Machines 390 0 0
Power Electronics 237 0 0
Power Systems 343 0 0
EMFT EE 9 0 0
Measurement 152 0 0
Engineering Mathematics 225 0 0
General Aptitude 206 0 0