Q#1 Power System Stability GATE EE 1991 NAT +2 marks -0 marks

A generator is supplying 1 per unit power to an infinite bus through the system shown in figure. Following fault at F, circuit breakers  and  open simultaneously. The  relationships in per unit are given by

Pre-fault condition:

During fault condition:

When  remain closed:

After  open:

Calculate the critical angel  before which breakers

 and  must open so that synchronism is not lost.

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 259 0 0
Signals and Systems 164 0 0
Control Systems 201 0 0
Analog Electronics 180 0 0
Digital Electronics 148 0 0
Electrical Machines 390 0 0
Power Electronics 237 0 0
Power Systems 343 0 0
EMFT EE 9 0 0
Measurement 152 0 0
Engineering Mathematics 225 0 0
General Aptitude 206 0 0