Q#1 Economic Load Dispatch GATE EE 2008 MCQ +2 marks -0.66 marks

A lossless power system has to serve a load of 250 MW. There are two generators (and ) in the system with cost curves and respectively defined as follows:

Where and are the MW injections from generator and  respectively. Then, the minimum cost dispatch will be

= 250 MW; = 0 MW

= 150 MW; = 100 MW

= 100 MW; = 150 MW

= 100 MW; = 250 MW

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 259 0 0
Signals and Systems 164 0 0
Control Systems 201 0 0
Analog Electronics 180 0 0
Digital Electronics 148 0 0
Electrical Machines 390 0 0
Power Electronics 237 0 0
Power Systems 343 0 0
EMFT EE 9 0 0
Measurement 152 0 0
Engineering Mathematics 225 0 0
General Aptitude 206 0 0