Q#1 Economic Load Dispatch GATE EE 2008 MCQ +2 marks -0.66 marks

A lossless power system has to serve a load of 250 MW. There are two generators (and ) in the system with cost curves and respectively defined as follows:

Where and are the MW injections from generator and  respectively. Then, the minimum cost dispatch will be

= 250 MW; = 0 MW

= 150 MW; = 100 MW

= 100 MW; = 150 MW

= 100 MW; = 250 MW

Sign in to see the solution

Log in to view the explanation, track your attempts, and keep your progress.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 268 0 0
Signals and Systems 168 0 0
Control Systems 262 0 0
Analog Electronics 186 0 0
Digital Electronics 150 0 0
Electrical Machines 399 0 0
Power Electronics 243 0 0
Power Systems 350 0 0
EMFT EE 111 0 0
Measurement 160 0 0
Engineering Mathematics 236 0 0
General Aptitude 221 0 0