Q#1 Economic Load Dispatch GATE EE 2026 NAT +2 marks -0 marks

A system with two generators G1 and G2 (without generator limits) is shown.

The total load on the system is 1184 MW. The expressions for the cost of generation ( and ) and real power loss () are as follows:

When the generators are operating at their optimal generation, meeting the total load requirement, the real power loss in the system is  MW (Round off to one decimal place)

Consider the Lagrange multiplier  for optimal generation.

Sign in to see the solution

Log in to view the explanation, track your attempts, and keep your progress.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 268 0 0
Signals and Systems 168 0 0
Control Systems 262 0 0
Analog Electronics 186 0 0
Digital Electronics 150 0 0
Electrical Machines 399 0 0
Power Electronics 243 0 0
Power Systems 350 0 0
EMFT EE 111 0 0
Measurement 160 0 0
Engineering Mathematics 236 0 0
General Aptitude 221 0 0