Q#1 Economic Load Dispatch GATE EE 1998 MCQ +2 marks -0.66 marks

In a power system, the fuel inputs per hour of plants 1 and 2 are given as         

         Rs per hour

  Rs per hour

The limits generators are:

 

 

Find the economic operating schedule of generation, if the load demand is 130MW, neglecting transmission losses

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 259 0 0
Signals and Systems 164 0 0
Control Systems 201 0 0
Analog Electronics 180 0 0
Digital Electronics 148 0 0
Electrical Machines 390 0 0
Power Electronics 237 0 0
Power Systems 343 0 0
EMFT EE 9 0 0
Measurement 152 0 0
Engineering Mathematics 225 0 0
General Aptitude 206 0 0