Q#1 Economic Load Dispatch GATE EE 2015 NAT +1 mark -0 marks

The incremental costs (in Rupees/MWh) of operating two generating units are functions of their respective powers  and  in MW, are given by         

 

where,   

For a certain load demand, and  have been chosen such that Rs/MWh and Rs/MWh. If the generations are rescheduled to minimize the total cost, then  is__________.

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 259 0 0
Signals and Systems 164 0 0
Control Systems 201 0 0
Analog Electronics 180 0 0
Digital Electronics 148 0 0
Electrical Machines 390 0 0
Power Electronics 237 0 0
Power Systems 343 0 0
EMFT EE 9 0 0
Measurement 152 0 0
Engineering Mathematics 225 0 0
General Aptitude 206 0 0