Q#1 Economic Load Dispatch GATE EE 2011 MCQ +2 marks -0.66 marks

A load center of 120MW derives power from two power stations connected by 220kV transmission lines of 25km and 75km as shown in the figure below. The three generators ,  and are of 100MW capacity each and have identical fuel cost characteristics. The minimum loss generation schedule for supplying the 120MW load is

 = 80MW + losses          

 = 20MW

 = 20 MW

 = 60MW

 = 30MW +losses

 = 30MW

 = 40MW

 = 40MW

 = 40MW + losses

 = 30MW + losses

 = 45MW

 = 45MW

Explanation Locked!

Unlock this branch to view the explanation, track, bookmark and more.

Sign in to Unlock
Browse Practice Questions by Chapters / Topics in Browse Practice Questions by Chapters / Topics in GATE Electrical Engineering
Total Questions

Attempted

% Attempted

Correct

% Correct

Topic Questions Attempted Correct
Network Analysis 259 0 0
Signals and Systems 164 0 0
Control Systems 201 0 0
Analog Electronics 180 0 0
Digital Electronics 148 0 0
Electrical Machines 390 0 0
Power Electronics 237 0 0
Power Systems 343 0 0
EMFT EE 9 0 0
Measurement 152 0 0
Engineering Mathematics 225 0 0
General Aptitude 206 0 0